Montenegro Paid China $40.7 Million for the Construction of the Highway

Montenegro’s Ministry of Finance paid the Chinese Exim Bank the fifth installment of the loan for the construction of the priority section of the Bar-Boljare highway, amounting to $40.7 million, Pobjeda reported. The ministry clarified that the amount of $32.79 million from...

Montenegro’s Ministry of Finance paid the Chinese Exim Bank the fifth tranche of the loan for the construction of the priority section of the Bar-Boljare highway in the amount of $40.7 million, Pobjeda reported Pobjeda.

The ministry clarified that the amount of $32.79 million relates to the principal, while the remaining $7.91 million relates to loan interest.

“The obligations to Exim Bank are denominated in US dollars, and when settling the obligations, Montenegro is obliged to provide dollars and repay the obligations in dollars. Given that, after exiting the hedging scheme, the state earned about $64.03 million, the stated amount will be used to pay the fifth installment. Therefore, there is no need to provide dollars to the market because they have already been provided, which avoids conversion costs,” the ministry said.

They added that if Montenegro had been required to provide dollars, without the hedging arrangement in place, the dollars would have been bought at the market rate, so the cost of the fifth installment in euros at the average CBM exchange rate on July 19 would have been about 36.2 million euros.

“If, on the other hand, the hedging agreement had continued under the same conditions defined by the 2021 agreement, which is impossible because market conditions have changed significantly and the agreement could not have been continued under the same conditions, the cost of the fifth loan tranche in euros would have been about 30.9 million euros,” the statement said.

So far, the government has paid the Chinese Exim Bank $208.7 million of the loan for the construction of the highway.

“Of this amount, $124.9 million relates to the principal, and $83.8 million is allocated to interest payments.” At the same time, it should be noted that interest payments began in 2015, while principal repayment began in 2021,” the Ministry of Finance said.

Repayment of the highway construction loan to date

The first loan installment was paid on July 21, 2021: principal repayment amounted to $29.21 million, and interest was repaid in the amount of $8.12 million. The second loan installment was paid on January 21 last year — the principal amount was $30.47 million, and interest was $8.2 million, Pobjeda recalls.

The third payment was made in July last year, with the principal amounting to $32.41 million and interest to $8.21 million, while the fourth installment was paid on January 21 this year — principal repayment amounted to $32.78 million, with $8.38 million repaid in interest.

The ministry reminded that the loan with Exim Bank was concluded in 2014, with a repayment period of 20 years and a six-year grace period.

“The final loan payment is due on January 21, 2035, when the loan will be repaid. A total of $786.9 million of the principal remains to be repaid,” the ministry said.

The priority section of the Bar-Boljare road was officially opened on July 13 last year, and the next day it was put into traffic. The total length of the first section of the highway is 41.5 km, including 20 bridges on the main route, nine bridges on the loop ramps, two overpasses, eight underpasses, 7.2 km of concrete walls, as well as 16 twin-tube tunnels.

The section has four interchanges with toll ramps, where the highway is connected to the existing network, namely Smokovac, Pelev Brijeg, Veruša and Mateševo (Smokovac, Pelev Brijeg, Veruša, Mateševo). The maximum speed is limited to 100 kilometers per hour.

Ten days ago, the highway operator Monteput said that since its opening, 2.16 million vehicles had used it, and nearly 8.75 million euros had been collected in tolls during that period.